LG Chem - Frequently Asked Questions
TIMELINE
DEC. 2023 Groundbreaking |
MARCH 2024 Building Construction |
MARCH 2025 Completion |
END OF 2025 Fully Operational |
INFRASTRUCTURE

- All infrastructure must be completed by End of 2025
- Utility upgrades ($11M paid for by LGC) Summer 2024
- Jostens Road Ext. to the rail, to begin Summer 2024
- Charles Bell Road Expansion: to begin Summer 2024
- Battery Way Construction to begin Oct. 2024
WAGE & COMMUNITY BENEFIT

- County reduced the tax burden owed over 20 years based on wages and investment.
- LG Chem is required to pay a minimum of $24/hour starting salary (200 six-figure jobs)
and contractually obligated to wages by PILOT agreement
ENVIRONMENTAL INFO
- All Environmental Concerns are regulated by the Tennessee Department of Environment & Conservation.
- LG is required to get permits and is regulated on air quality, water, waste and many other factors.
- LG Chem requires a minor source air quality permit —the lowest environmental impact for air quality concerns.
- LG Chem will manage all wastewater pretreatment on site before being discharged to Clarksville Gas & Water.
- Building located 600ft off the road with 40 acre buffer.
QUESTIONS: Josh Ward, joshward@clarksville.tn.us
INTERESTED TRADE PARTNERS: PREQUALIFY WITH JE DUNN
|
 |